Budgeting a renovation in Thailand, from the quote to the last box

A builder can quote the roof by the metre, insulation by the roll and tiles by the box. Compare the work each price buys before adding the figures to your budget.

Illustration of an unfinished single-storey home with a covered veranda
San Kamphaeng case study · ฿1,013,020 across 16 trades. House illustration.

What work does the builder’s total include?

One San Kamphaeng quotation includes both an extension roof and work on the existing roof. Its foundation area covers only part of the job. Before comparing renovation with rebuilding, price both options for the same finished floor area and specification.

Compare renovation and rebuild costs

How many rolls will cover the ceiling?

The 118.16 m² ceiling example needs 50 rolls at 2.40 m² per roll. Adding a 5% cutting allowance takes the order to 52. Use the measured ceiling area and the usable coverage printed on your chosen pack.

Price an insulation order

How far does a tile allowance go?

A 102 m² floor with a 10% cutting allowance needs 112.20 m² of tile before rounding up to whole boxes. Compare the two whole-box orders, then check which area the builder used for the tile allowance and whether laying materials are included.

Compare two tile orders